An industrial trade park had 26 traffic bollards which were in need of refurbishment.

They were rusted and the paint was worn and flaking off. 4 of these bollards has been damaged and were leaning at angles.

Why MODA?:

We have built a great working relationship with this client to be able to complete a diverse portfolio of works to the highest possible standard, and turn it around quickly.

Client Brief:

To remove and replace 4 x damaged bollards and refurbish all bollards on site.

MODA Solution Completed:

Firstly we excavated, removed and replaced the damaged bollards.

We then prepared and re-painted all bollards.

After a discussion with our client, we recommended a specialist paint, in different colours to those used previously to achieve a more aesthetically pleasing and more durable finish.

Project Gallery

Before - Bollards
After - Bollards

Ready to talk Projects?

Our team at MODA are ready to talk to you about your projects.
From large scale commercial, to residential extensions, refits and rebuilds, we can talk you through new designs, structural and practical construction projects from start to finish.