12 Weeks
Sub £125,000
Project Development
Client:
Western UK Property Group
Problem:
A new development of 11 properties in Manchester had been left partly completed, the developer had a significant investment that could not be realised with the part finished scheme.
Why MODA?:
MODA Contracting understood the difficult position the developer was in, and through meetings onsite, we were able to agree a resolution that would see the scheme through to completion, whilst at the same time ensuring all the M&E and works completed by prior contractors was thouroughly checked with any repairs or remedial works completed.
MODA Solution Completed:
MODA Contracting started by auditing all the M&E and working with consultant to ensure requirements were met or exceeded. The 11 units in varying states were then all fully completed including decoration and floor finishes with a new electric gated entry and communal lighting to external areas.